Which repeat machine failure deserves a five-whys sheet?

Add up the hours your machines were down for each cause and start with the cause that has the most. On a cause sheet, one page per failure, you write the chain of whys, proof beside each answer and a date to count the hours again.

Published Updated 22 min read
In this article

A hydraulic hose bursts on the header of your combine for the third time this harvest. Replacing it each time does not tell you why it keeps bursting. On the example farm in this article, that hose alone accounts for 48 of the 100 hours of stoppage in one harvest (the hours are made up for the example).

Add up the hours your machines were down for each cause. Take the cause with the most hours and ask why about it up to five times, until you reach an answer you can change in how the farm works and check later. This is the five whys. Keep the record on a cause sheet, one page per failure. It holds the chain of whys, proof beside each answer (a part you kept, a photo, an invoice), the change and the date to add up the hours again.

The only machine case in the sources listed at the end comes from sugarcane, not from grain. It is the stoppage log of one sugarcane harvester over 107 days in Brazil. Three parts of that machine stopped it for 66.38, 29.70 and 27.35 hours. The first was the elevator that lifts the cut cane out of the machine. The second was the undercarriage it rides on (the tracks or wheels and their frame). The third was the base cutter that cuts the stalk at the ground. The two longest lines in the log, 112 and 75.52 hours, tie their hours to no specific part, so no why could start from them.

For the hose, the chain runs like this. The hose rubbed against the frame, because a clip was missing, because the clip was not refitted after the off-season service, because the service checklist has no step for it. The checklist is something you can change and check later, so the chain stops there. The full chain, with its proof, is shown further down.

This is not a promise of fewer hours of stoppage. The method comes from factories and is used in health care, and none of the sources tests it on a grain farm. The section on evidence below says what they do contain.

Which failure should get a sheet first?

The one with the most hours of stoppage in your own log, the notes of each stop with its date, hours and cause. Work on one failure at a time, so that the first sheet is finished before the next begins. Count hours, not stops, because a stop costs the time the machine is down.

Hours do not all weigh the same: an hour lost at the peak of planting or harvest costs more than one in the off-season. If that matters on your farm, also add up the peak weeks alone and see whether the order of the causes changes; keep the full count as the starting point.

A Pareto chart lists the causes from the most hours to the fewest. Each has its share of the total and a running total (its hours added to those of the causes above it). The Institute for Healthcare Improvement (IHI) is a US non-profit that publishes improvement guides for health care. It describes the Pareto principle as roughly 80 percent of an effect coming from 20 percent of the causes. It calls the causes at the top the “vital few”, the ones that matter most. That split is a pattern and not a law, so follow your own count and not the rule.

An undergraduate thesis by Pizzeco at the Federal University of Uberlândia, in Brazil, used the count on one sugarcane harvester at one mill. The harvester worked 107 days, from 19 July to 3 November 2018, against a target of availability above 85 percent (availability is the share of the time the machine is ready to work). Its stoppage log had two catch-all lines, “miscellaneous”, 112 hours, and “preventive service” (planned work, not a failure), 75.52 hours, and neither ties its hours to a specific part. Pizzeco set both aside. Three parts were left: the elevator with 66.38 hours, the undercarriage with 29.70 and the base cutter with 27.35.

Figure: Hours of stoppage by line of the log, one sugarcane harvester, 107 days. Source: Pizzeco (2019), Federal University of Uberlândia; the two longest lines were set aside by the author
The two longest lines of the log named no part and could not be analyzedHours stopped: miscellaneous 112 and preventive service 75.52, both set aside because no part was named; elevator 66.38, undercarriage 29.70 and base cutter 27.35, analyzed with five whys.Hours stopped, one harvester, 107 daysMiscellaneous (no part named)112 hPreventive service (no part named)75.52 hElevator66.38 hUndercarriage29.70 hBase cutter27.35 hSet aside: no part namedTaken to five whys

A log line that names no part can hold the most hours and still give you nothing to ask why about. Pizzeco suggests that the work order carry the part and the hour-meter reading at the moment of the stop, and found stops with no hour-meter reading written down. The article on the factory service interval sets that reading against the manufacturer’s schedule.

On the example farm, one soybean harvest’s log adds up to 100 hours of stoppage. The hours are made up for the example.

Hours of stoppage by cause on the example farm, one harvest
Cause Hours stopped Share of total Running total
Hydraulic hose bursts on the header 48 48% 48%
Header drive-chain slips 24 24% 72%
Tire punctures 12 12% 84%
Sensor faults 10 10% 94%
Other, each under 4 hours 6 6% 100%

The hose line gets the first sheet and the drive-chain line is next. The count needs only a log that gives the hours and the part for each stop. If yours does not, the section on what goes on the cause sheet, further down, shows what to record from the next stop on.

How do you ask why five times?

Write the failure in one precise sentence, then ask why. Serrat’s note for the Asian Development Bank, an international development bank, gives the steps. State the problem and agree on the statement with the people involved, write the answers to the first why and ask why again about each answer. Then look for causes in the way the work is set up, not in one person, and decide what to change. Serrat says Sakichi Toyoda developed the technique for Toyota Industries Corporation.

Five is “a good rule of thumb” in that note, and not a target. You may need fewer whys, or more. The chains in the thesis run from three to five answers.

Serrat also encourages the people involved to verify each answer on the spot before the next why. On the cause sheet you turn that into a column: beside every answer, write what proves it true, such as a part you kept, a photo, an invoice or an hour-meter reading. A reading is only as good as the meter, so if the meter and the fuel bought do not match, start with that gap. An answer with nothing beside it is a guess, and the next why stands on it.

Figure: The five whys of the hose line, with the proof beside each answer. Source: example chain; the Serrat steps and the proof on the spot
Five answers, each with a proof, end in a step missing from the service checklistHose split, hose rubbed on the frame, clip missing, clip not refitted after the off-season service, service checklist has no step for refitting clips. The change is to add that step.Failure: hydraulic hose burst on theheader, 48 hours stoppedWHY 1A hose on the header split open.Proof: the hose, kept, and the workorderWHY 2The hose had rubbed against the frame.Proof: photo of the worn spot on the oldhoseWHY 3The clip that holds the hose wasmissing.Proof: photo of the frame without theclipWHY 4The clip was not refitted when theheader went back on after theoff-season service.Proof: the invoice lists header removaland no clipWHY 5The service checklist has no step forrefitting hose clips.Proof: the checklist itselfTHE CHANGEAdd the step to the checklist, with anowner and a date.

The chain for the hose line has five answers, each with its proof, and all of it is made up for the example. The first four describe what happened to the hose and its clip. The fifth, a step missing from the service checklist (the list of steps the workshop follows at each service), is something the farm can change and later check.

Where does the chain stop?

At an answer the farm can change and check. IHI’s own tip for its cause-and-effect diagram is the same test: keep asking why until the cause is specific enough to test a change and measure its effects. IHI’s page on the five whys adds that what looks like the cause is sometimes just another symptom.

Two kinds of answer fail the test. One is a person’s name, or a word like careless. The RCA2 guide is a 2016 manual on finding why harm happened in hospitals, written by the National Patient Safety Foundation, a US patient-safety group. It says a human error always has a cause before it, and so does a procedure that was not followed. So neither is a root cause, the cause at the bottom of the chain. The other kind is a vague word such as poor, inadequate or wrong, which RCA2 tells analysts to replace with what actually happened. RCA2 was written for hospitals, so this article borrows only its rules for wording an answer.

The thesis ran five whys on the wear of the base-cutter blades, shown below. The blades rub the soil. The operators avoid the height regulator, the control that sets how high the base cutter rides, because the machine sways as it follows the ground. The chain ends on the base-cutter pressure (how hard the cutter is pressed down), which is poorly calibrated when the regulator is used.

The author concludes that the operators lacked information on how to calibrate that pressure. But the last answer says only “poor”, a word of the kind RCA2 says to replace. The question under the figure, which pressure and who sets it, is this article’s own and not the thesis’s. On your own sheet you would write the answer to it.

Figure: The five whys for the base-cutter blades in the thesis, shortened. Source: Pizzeco (2019), table 4; the last line is an added question
The thesis chain ends on a poor calibration that does not say which pressure or who sets itWorn blade tips, blades rubbing the soil, height regulator not used, operators uncomfortable with the swaying of the machine, poor calibration of the base-cutter pressure when the regulator is used.Failure: excessive wear of thebase-cutter bladesWHY 1The blade tips wear down too fast.WHY 2The blades rub the soil while cutting.WHY 3The base-cutter height regulator is notused.WHY 4The operators are uncomfortable withthe constant swaying of the machine asit follows the ground.WHY 5Poor calibration of the base-cutterpressure when the regulator is used.NEXT QUESTIONWhich pressure, and who sets it?

The thesis also ran five whys on the elevator, the part that lifts the cut cane out of the machine. In two of those chains the last answer is that the mill’s service truck (the workshop on wheels that goes out to the machines) lubricated the part at irregular times. The author’s own reading of those chains is that the mill had set no fixed lubrication interval. That is the kind of answer the RCA2 rule above asks for: the irregular lubrication is not blamed on the people, because a missing interval stands behind it.

What does the fishbone add?

A chain follows one answer downward. The fishbone (also called the Ishikawa diagram after its creator) is a diagram that lays out the branches of causes side by side. IHI describes it as a diagram with the effect in a box at one end and the causes grouped under Materials, Methods, Equipment, Environment and People, in branches that resemble the bones of a fish.

On the cause sheet you use it as a check and not as a drawing. Label each answer of the chain with one of the five (Equipment means the machines and tools), and see which nobody has asked about. On the example farm the chain covers Equipment and Methods, and three branches are still open. RCA2 asks teams to find several contributing factors and not to stop when one turns up.

IHI calls these five categories the classic set, the usual starting point, and lets a team choose five or six that fit its problem. Open a second sheet for a branch when the answer you found there is itself a failure that repeats in your log, or when the hours behind it justify the work.

Figure: The five fishbone categories checked against the hose chain. Source: IHI categories; the chain is the example from the previous figure
The hose chain covers Equipment and Methods, and three categories are still openEquipment and Methods are covered by whys 2 to 5. Materials, People and Environment are not asked yet.Fishbone check of the hose chainEQUIPMENTWhys 2 and 3: the hose rubbed on theframe; the clip that holds it wasmissingMETHODSWhys 4 and 5: the clip was not refittedafter the service; the checklist has nosuch stepMATERIALSNot asked yet: the type and age of thehosePEOPLENot asked yet: what the person whorefits parts after a service is told tocheckENVIRONMENTNot asked yet: heat and dust where thehose runsCovered by the chainNot asked yet

How much evidence stands behind five whys?

The method is described in a note from a development bank, in health-care improvement guides and in a patient-safety guide. The only study on a farm machine among the sources listed at the end is the undergraduate thesis on one sugarcane harvester. It measured the stoppage hours and proposed a maintenance plan, and did not measure whether the hours fell afterwards. The sources hold no test on a grain farm and no comparison of farms that keep the sheet with farms that do not. That does not mean the method fails. It means nobody has measured it on a farm like yours.

Serrat lists the criticisms. Whoever investigates stops at symptoms, cannot go beyond what they already know and gets little help in asking the right questions. Different groups of people also reach different causes for the same problem. IHI’s page says the same of people who see different parts of the work. For that reason, whoever fills in the sheet writes proof beside each answer, so that the next person can check it.

Figure: What the sources contain and what they lack on five whys. Source: Serrat (2009), IHI (2017), RCA2 (2016), Pizzeco (2019), as read in October 2026
Three kinds of description in the sources, no test on a farm and no measure of the resultIn the sources: a development bank note, health-care improvement guides, one undergraduate study of one cane harvester. Not in the sources: a test on a grain farm, a measure of whether stoppage hours fell, a comparison of farms with and without the sheet.In the sourcesA note from a development bank (2009)Health-care improvement guides (2016,2017)One undergraduate study of one caneharvester at one mill (2018 harvest)Not in the sourcesA test on a grain farmA measure of whether the stoppagehours fell afterwardsA comparison of farms with and withoutthe sheet

What goes on the cause sheet?

One page per failure, with the seven fields in the table. Copy them onto a blank page. Start from the stoppage log of the last harvest. Use the dealer’s repair history for each machine to fill what the log lacks, such as the part or the date (the article on what repairs cost per machine shows where to ask). If the log names no part on its lines, you cannot start a sheet yet. For the next stops, write the part and the hour-meter reading on every line, and start the first sheet when you have enough stops to add up.

The blank cause sheet, one page per failure
Field What you write
Failure The failure in one precise sentence, the machine and the dates
Hours stopped The hours from your log and their share of the total
Whys Up to five lines: each answer, with its proof beside it
Fishbone check Materials, Methods, Equipment, Environment, People: answered or not asked yet
Cause to change The last answer, the one the farm can change and later check
Action The change, who makes it and by what date
Count again The date when you will count the hours stopped by this cause again

The figure below is the same page filled in for the hose line.

Figure: The cause sheet of the hose line, filled in. Source: example sheet; the fields follow the steps of the article
One page holds the failure, the count, the chain, the check, the change and the date to count againFields: failure, hours stopped, chain, fishbone check, cause to change, action, and count again. Values are from the hose line of the example farm.Cause sheet, one failure per pageFAILUREHydraulic hose burst on the headerHOURS STOPPED48 of 100 logged, 48 percent, firstin the countCHAINFive whys, with proof beside eachanswerFISHBONE CHECKEquipment and Methods answered;Materials, People and EnvironmentopenCAUSE TO CHANGEThe service checklist has no step forrefitting hose clipsACTIONAdd the step; owner and date writtenon the sheetCOUNT AGAINHose stoppage hours after the nextharvest

The same page takes any failure that repeats, not only a stopped machine. Harvest loss above your limit also repeats. Split the loss between the header and the inside of the machine, as the article on the harvest-loss limit shows, and start the chain with the larger part. Plan about two hours for the first sheet.

The cause you end on is usually a missing step or a task nobody owns, and the change is to add the step, name who does it and count again. That is farm management at work; see farm management, and the production articles for other production records. Related: Where is each tool and part kept in your farm shop?

Provenance

Derives from
  1. Serrat, O., The Five Whys Technique, Knowledge Solutions, Asian Development Bank, February 2009
  2. Institute for Healthcare Improvement, 5 Whys: Finding the Root Cause, web page consulted on 27 October 2026
  3. Institute for Healthcare Improvement, QI Essentials Toolkit: Cause and Effect Diagram, 2017
  4. Institute for Healthcare Improvement, QI Essentials Toolkit: Pareto Chart, 2017
  5. National Patient Safety Foundation, RCA2: Improving Root Cause Analyses and Actions to Prevent Harm, Version 2, January 2016
  6. Pizzeco, M. M., Aplicação da engenharia de manutenção em colhedoras de cana de açúcar numa usina sucroalcooleira do Triângulo Mineiro: um estudo de caso, undergraduate thesis in Production Engineering (in Portuguese), Universidade Federal de Uberlândia, 2019
What this article covers
Choosing which repeat failure gets a cause sheet by counting the hours of stoppage by cause; asking why up to five times with proof beside each answer; checking the five fishbone categories (materials, methods, equipment, environment, people); and the fields of the sheet that records it.
What it does not cover
How to repair a machine, which maintenance plan to adopt, or how many hours a farm will save. The sources listed at the end describe the method and one undergraduate case that did not measure its result, and none of them tests it on a grain farm.
Published
Updated
Error found
Point out an error and the article is corrected with a note on what changed.

How to cite this article

Rurivia. (2026, October 27). Which repeat machine failure deserves a five-whys sheet? https://rurivia.com/en/library/production/repeat-failure-cause-sheet/


Keep reading

Production

How to tell whether deep tillage or a terrace worked

The field was ripped because it was the third year, and the terrace was rebuilt after a wet one. With no reading taken first, nobody can say afterward whether either job changed the ground.

Aug 27, 2026
Production

Vaccination calendar: which animals have no record?

A farm of 200 head that cannot say which 32 have no dated dose ends up asking the veterinarian about 200. A calendar by lot, a count and a review date with a name cut the question to 32.

Oct 28, 2026
Production

Field yield fell: the variety, the field, or the year?

A low harvest in the back field looks like the variety's fault. Often it was the year or the field, and only the field's own series, set against the farm average each season, tells them apart.

Sep 7, 2026
Production

Stocking rate: how much is each pasture carrying, and when?

A single head-per-hectare figure for the whole year hides the load, the kilograms of animal live weight on each hectare. The load changes as the animals grow and as the pasture changes with the season. Record each pasture and season in its own block, with the animals' weight and a forage reading written beside the head count.